Mars Mission 2016 – PROJECT SCHEDULE
Earth-Based
Orbital Transfer Vehicle (OTV)
- Design/Test OTV Main Propulsion – 1 JUL 2003 to 1 JAN 2007
- Design/Test OTV Structure/Systems – 1 JUL 2005 to 1 JAN 2010
- Construct OTV/CS Production Facilities – 1 JUL 2007 to 1 JUL 2010
- Construct OTV Modules – 1 JUL 2010 to 1 SEPT 2013
- Specialize OTV Modules – 1 SEPT 2011 to 1 MAR 2014
- Final OTV Modules Ground Systems Test – 1 SEPT 2012 to 1 JUN 2014
- Delivery of OTV Modules/Prep for Launch – 1 AUG 2013 to 1 OCT 2014
- Launch OTV Modules – 15 FEB 2014 to 1 JAN 2015
Crew Shuttle (CS)
- Design/Test CS Main Propulsion – 1 JUL 2003 to 1 JAN 2007
- Design/Test CS Structure/Systems – 1 JUL 2005 to 1 JAN 2010
- Construct OTV/CS Production Facilities – 1 JUL 2007 to 1 JUL 2010
- Construct OTV Modules – 1 JUL 2010 to 1 SEPT 2013
- Specialize OTV Modules – 1 SEPT 2011 to 1 MAR 2014
- Final OTV Modules Ground Systems Test – 1 SEPT 2012 to 1 JUN 2014
- Delivery of OTV Modules/Prep for Launch – 1 AUG 2013 to 1 OCT 2014
- Launch OTV Modules – 15 FEB 2014 to 1 JAN 2015
Earth Orbit
Orbital Transfer Vehicle (OTV)
- Construct OTV 1 MAR 2014 to 1 FEB 2015
- Outfit and Supply OTV 1 JAN 2015 to 1 JAN 2016
- Final Systems Testing OTV 1 JAN 2016 to 1 FEB 2016
- Crew Prep of OTV 1 JAN 2016 to 15 FEB 2016
- Launch OTV 11 MAR 2016
Crew Shuttle (CS)
- Construct CS 1 DEC 2014 to 1 MAR 2015
- Outfit and Supply CS 1 JUN 2015 to 1 JAN 2016
- Final Systems Testing CS 1 JAN 2016 to 1 FEB 2016
- Crew Prep of CS 1 JAN 2016 to 15 FEB 2016
- Launch CS 24 FEB 2016
Earth/Mars Transfer
Mars Orbit
Mars-Based
OTV – Orbital Transfer Vehicle (ESS Carl Sagan)